Infrastructure ProjectsDHAI-R Islamabad & Rawalpindi
DHA Phase 3
Infrastructure and development works carried out in DHA Phase 3, Islamabad-Rawalpindi.
Constructionof 315 Feet long and 50 Feet high stone concrete and RCC wall
The scope of the work included:
- »Excavation and back filling
- »Usage of Jack hammer in Rocky strata
- »Plum concrete
- »Steel & Form work
- »Concrete of RCC wall 315 Feet long and 30 Feet high
- »Gabion works
- »Stuck pointing

Constructionof 600 FT RCC Drain with Culvert
The scope of the work included:
- »Excavation in rocky area, slush removal, back filling
- »Diversion of existing water stream
- »Construction of 500'x30'x12' RCC Drain and 80'x30'x12' Two cell culvert